Minority owned business among those seeking millions in unpaid services at obama library

Minority Owned Business Among Those Seeking Millions in Unpaid Services at Obama Library

Posted by
2 mins read
July 23, 2026
Several subcontractors say they are still owed money for work on the $850 million Obama Presidential Center, while the Obama Foundation says it has no direct contracts with those companies and no payment dispute with the project's construction manager.

CHICAGO, Ill. – Payment disputes involving subcontractors that worked on the Obama Presidential Center have drawn renewed attention following the opening of the landmark campus, with several firms claiming they are still owed millions of dollars for completed work.

One black-owned business has escalated the claims and filed a lawsuit demanding payment.

The Obama Foundation, which oversees the project, says responsibility for hiring and paying subcontractors rests with the project’s construction manager, Lakeside Alliance, and that it has no outstanding financial dispute with the joint venture.

Subcontractors claim unpaid invoices

The issue first gained widespread attention after Crain’s Chicago Business reported that multiple subcontractors—including several minority-owned businesses—said they had not been fully paid for work performed during construction.

According to the report, contractors described a project plagued by delays, design changes and disputes over change orders. Several said those changes significantly increased costs while leaving smaller companies responsible for expenses they had not anticipated.

Omar Shareef, president of the African American Contractors Association, told Crain’s that several subcontractors had sought his assistance in recovering unpaid balances.

Shareef said approximately 10 subcontractors had contacted his organization, including both Black-owned and white-owned businesses. He estimated the value of disputed claims at roughly $100 million, although that figure includes a separate $40 million lawsuit filed by one subcontractor.

Obama Foundation says it is not responsible for subcontractor payments

The Obama Foundation disputes claims that it owes money directly to subcontractors.

In a statement provided to FactCheck.org, the foundation said Lakeside Alliance served as construction manager and had “primary responsibility” for hiring and managing subcontractors throughout the project.

The foundation also said it has “no outstanding disputed charges with Lakeside” and “no direct legal agreements or contracts with Lakeside’s subcontractors.”

According to the foundation, it worked with Lakeside Alliance to help some struggling subcontractors by supporting accelerated payments or prepayments when appropriate.

“We chose Lakeside Alliance as an experienced construction manager that was also committed to going above and beyond to help prepare its subcontractors to handle this project and mentor smaller firms who had never worked on a project of this scale,” the foundation said.

Legal disputes extend beyond payment claims

One of the largest legal actions connected to the project was filed by a Black-owned subcontractor seeking approximately $40 million in damages. The lawsuit alleges racial discrimination and disputes involving structural engineering work and project overruns.

Separately, construction of the presidential center faced years of litigation over its location in Chicago’s Jackson Park. Opponents challenged the city’s use of public parkland for the project, but those lawsuits were ultimately dismissed, and the U.S. Supreme Court declined to hear an appeal in 2021.

Project costs grew significantly

The Obama Presidential Center officially opened in June after years of construction.

The campus includes a museum, public library branch, athletic and community facilities, and public gathering spaces honoring the legacy of President Barack Obama and First Lady Michelle Obama.

Project costs increased substantially during construction. While early estimates placed the project between $300 million and $500 million, the Obama Foundation confirmed the final estimated cost reached approximately $850 million.

Phil Stilton

Phil Stilton is the Editor and Publisher of Shore News Network, an independent digital newsroom providing original reporting on New Jersey, national news, government, public policy, public safety, courts, and community affairs.

As founder of the publication, Stilton leads editorial strategy, investigative reporting, and daily newsroom operations while overseeing coverage that reaches millions of readers annually.

With extensive experience covering municipal government, county government, state legislatures, elections, law enforcement, emergency management, and public records, Stilton specializes in translating complex government actions into clear, factual reporting. His work frequently relies on primary source documents, including court filings, legislation, public meeting records, election finance disclosures, government databases, police reports, and Freedom of Information and Open Public Records Act (OPRA) requests. He has reported extensively on local government accountability, taxpayer spending, campaign finance, public corruption investigations, infrastructure, public safety, and the policies affecting New Jersey residents.

Under Stilton's editorial leadership, Shore News Network has grown into one of New Jersey's largest independent digital news organizations, publishing thousands of original news articles each year while providing breaking news coverage, investigative reporting, and analysis across state and local government. The publication's reporting is routinely sourced from official government agencies, public officials, court records, and firsthand documentation, with a commitment to transparency, attribution, corrections when warranted, and clearly distinguishing factual reporting from opinion.

Stilton's journalism follows established newsroom standards emphasizing accuracy, verification, fairness, and accountability. Every effort is made to verify information through official records and multiple reliable sources before publication. His reporting is intended to provide readers with timely, well-documented information that helps them understand the issues affecting their communities, while maintaining editorial independence from political parties, government agencies, advocacy organizations, and commercial interests.

Readers can submit story tips, corrections, public records, or media inquiries through the official Shore News Network website or its verified social media channels. Shore News Network welcomes corrections and updates when new information becomes available as part of its ongoing commitment to accurate and transparent journalism.